Description
The Biscay Marine Energy Platform (BiMEP) is an open-sea facility to support research, technical testing and commercial demonstration of pre-commercial prototype utility-scale floating Marine Renewable Energy Devices or MREDs. BiMEP provides manufacturers of such devices with ready-to-use facilities to validate their designs and to test their technical and economic feasibility.
BiMEP occupies a 5.3 km2 marked area excluded for navigation and maritime traffic and located at a minimum distance of 1,700 m from shore, close enough for fast access. The water depth in this area ranges from 50 to 90 m. The total power of 20 MW is distributed over four offshore connection points of 5 MW each.
Each berth is connected to the onshore substation via a dedicated three-phase submarine cable in series with a land three-phase line, both at 13.2 kV. The onshore electricity substation houses electrical protection systems, measurement systems and transformer, allowing the berths to be connected up to the national power grid. The berths are fitted with commercial power and fibre optic connectors to enable swift connection and disconnection of MREDs.
Location
Located off the coast of Armintza, in the Basque Country, northern Spain.
Licensing Information
The technological development and the geographical characteristics of the Basque Country provide suitable preconditions for the production of marine energy, including wave and offshore wind. Furthermore, the presence and level of development of the naval industry in the Basque Country are determinants for the wave energy sector to be considered as a strategic and promising sector in the Basque Country. In this context, in 2008 the Basque Energy Board (Ente Vasco de la Energía-EVE) set the BiMEP project in motion.
The installation of BiMEP was administratively complex; it involved the participation of both national and local administrations. Several ministries and departments participate in different sections/steps of the administrative process. Such administrative process generally shares the following common structure:
- Step 1: consult with the Spanish Ministry for Environment, Rural and Marine Affairs (the Spanish environmental agency) about the need for conducting an Environmental Impact Assessment
- Step 2: Apply for the administrative authorisation from the Spanish Ministry of Industry, Tourism and Trade to conducting the works and for the declaration of Public Use from the Provincial Industry and Energy Dependency of the Spanish Government Delegation in Bizkaia
- Step 3: apply for the concession of marine-terrestrial public domain, which is a two-step process and involves the Spanish Ministry of Public Works and the Ministry for Environment, Rural and Marine Affairs.
Step 1: in accordance with Article 16 of Royal Decree 1/2008, the Promoter (EVE) initiated the environmental procedure in 2008. In order for the Ministry to make an informed decision on whether or not an Environmental Impact Assessment was needed, three documents/steps were required:
- 1A. Project submission, including the objective, description and location of the project
- 1B. Submission of an environmental analysis document, covering the following aspects: a) actions that may cause environmental impacts throughout the different stages of the project (i.e. planning, construction, operation and abandonment), b) potential environmental impacts of the project, c) mitigation and corrective measures/strategies to offset the potential negative environmental impacts, and d) an Environmental Monitoring Plan of the project.
- 1C. Consultation with stakeholders, which is to be carried out by General Directorate for Environmental Quality and Evaluation of the Spanish Ministry for Environment, Rural and Marine Affairs. In this case, the consultation process included key stakeholders, such as fishermen guilds (cofradias[1]) and environmental NGOs, amongst others.
A preliminary Environmental Impact Study (EIS) of the BiMEP Project was undertaken in July 2008 by AZTI-Tecnalia. The full EIS was commissioned by EVE and carried out by AZTI-Tecnalia in December 2008.
In April 2009, the General Directory of Quality and Environmental Evaluation of the Spanish Ministry of Environment, Rural and Marine Affairs requested additional information about the project and its impacts. In order to respond to this request, in April 2009 the complete EIS was sent to the above mentioned General Directory and, in parallel, a personal meeting was held with their representatives.
Based on a detailed analysis of these three documents/steps, the Spanish Ministry for Environment, Rural and Marine Affairs made the decision for BiMEP not to be subject to the full Environmental Impact Assessment process in June 2009. The analysis of the EIS had concluded that no significant environmental impacts were expected as a result of the implementation of the BiMEP project. Furthermore, most stakeholders consulted about the potential affection of the BiMEP did not envisage significant impacts on habitats, protected species or environment as a result of the implementation of the BiMEP.
Due to the uncertainties around environmental impacts and the lack of reference data, the Environmental Statement recommended the implementation of the environmental monitoring program suggested in the Environmental Impact Study.
Step 2: For obtaining the administrative authorisation and public use declaration of the installation of the BiMEP infrastructure, the Promoter (EVE) submitted to Spanish Ministry of Industry, Tourism and Trade and the Provincial Industry and Energy Dependency of the Spanish Government Delegation in Bizkaia several documents, which included, a) the preliminary draft of the project, b) an environmental analysis document, and c) an economic evaluation analysis document.
In accordance with the provisions of Articles 125 and 144 of Royal Decree 1955/2000 and Article 27 of Royal Decree 1028/2007, the preliminary draft was submitted for public consultation and reprints were sent to key administrations and stakeholders:
- The City Council of Lemoiz, the General Directorate for Planning, the General Directorate of Ports and Maritime Affairs, and the General Directorate for Fisheries and Agriculture of the Basque Government, as well as the Basque Water Agency did not provide any feedback.
- On the other hand, the Department of Public Works of the Provincial Council of Bizkaia, the Bilbao Bizkaia Water Consortium, the General Directorate for Fisheries and Aquaculture of the Spanish Ministry for Environment, Rural and Marine Affairs, Iberdrola (Spanish energy company) and one local citizen did provide feedback, indicating interest mainly on technical aspects, to be considered in drafting the execution project. All requests for additional information were duly addressed by EVE at this stage.
Based on the outcome of the consultation process, the Spanish Ministry for Industry, Tourism and Trade (of the General Directorate for Energy Policy and Mining) authorized, in 2011, the installation of BiMEP, and stated its declaration of public use.
Step 3: In 2011, the Promoter (EVE) proceeded to tackle the final step and obtain the concession of marine-terrestrial public domain which was granted on the 6th of February 2012.
Once authorisation for the project execution was granted, contracts were awarded for the supply and installation of submarine power lines and ground cables, in November 2012 the first works started with the horizontal drilling for the installation of the submarine power cables. In September 2013 the works for the installation of submarine cables started.
The environmental monitoring program started in August 2011 in its preoperational phase and was undertaken by AZTI-Tecnalia. During construction works, the environmental monitoring for the construction phase was carried out.
BiMEP was officially inaugurated in July 2015.
During the public consultation process of the EIS in the framework of the EIA process in Spain, some amendments and comments to the EIS developed in 2016 were done by different stakeholders. Thus, in 2018 a new EIS was developed by AZTI in order to correct, respond and improve those aspects and amendments indicated during this public process. This new EIS was presented in February 2018.
On the 31th of May 2018, the Ministry of Agriculture, Fisheries and Food and Environment of the Spanish Government decided to grant environmental approval to offshore wind testing and demonstration projects at the BIMEP test site.
[1] Spanish cofradias (fishing guilds) are institutions with and old tradition that in some cases dates back many centuries. Their aim is to assure collective economic exploitation of fishing resources in coastal area. The cofradias are the institutional system for more than 80% of the employment in fisheries in Spain. In addition, more than 50% of landings are under the control of cofradias. It is a clear distinction between cofradias and other organizations such as boat owners associations or producer organizations. The cofradias are related exclusively to coastal fisheries while the other organizations deal with industrial fisheries. The cofradias are organized democratically and both the crew and the boat owner have representatives in the executive bodies. These institutions are well recognized by the Spanish and regional law and can propose management rules in their area of influence such as fishing time, allowed fishing gear and area and time closures. The rights of cofradias can be considered a form of territorial use rights in fisheries (TURFs).
Project Progress
The test centre was inaugurated and fully operational in July 2015.
Activity to date:
- MARMOK-A-5: BiMEP hosted the first floating wave energy device connected to the grid in Spain, the MARMOK-A-5 device developed by Oceantec (IDOM). The transport to site operation of the WEC, so-called MARMOK-A-5, and its installation at BiMEP was completed on 12 October 2016. MARMOK-A-5 was an OWC point absorber 5 metres in diameter, 42 metres in length and 80 tonnes in weight. The generating system comprised two air turbines located in the upper part of the device with a rated capacity of 30 kW, which were previously tested at the Mutriku wave power plant. The device was connected to the grid in early December delivering the first kWhs on 13 December 2016. The technology development was supported by the Basque Energy Agency – Ente Vasco de la Energía (EVE) under a Pre-commercial Procurement Contract. A second phase of testing activities of the WEC were also carried out as part of the European project OPERA, that ended in July 2019.
- Penguin (WELLO): In August 2021 Finnish company WELLO completed the installation of its Penguin device in BiMEP. It is a direct drive, 44m long, 600kW rated power device. Grid connected testing of the Penguin device will start in September 2021.
- DemoSATH (SAITEC): The first floating wind energy device to be installed in BiMEP is a 2MW wind turbine with rotor height 79 m and mounted on a 65 m x 30 m concrete platform developed by Saitec. Moorings and mooring lines were installed in September 2022 and installation of the device is currently ongoing (November 2022)
Regarding ancillary equipment testing, there are several prototypes being tested in the area:
- HarshLab 2.0 by Tecnalia, an offshore laboratory that enables testing of new materials and solutions against corrosion, ageing and fouling in the marine environment, was installed in summer 2022. The installation of Harshlab 2.0 follows the successful testing of Harshlab, installed in summer 2018 and decommissioned in August 2021
- Basque company ZUNIBAL tested metocean buoys under the ANTEIA project. Subsequently Anteia buoys have been used in the BiMEP area as wave data suppliers
- In 2017, company DITREL tested their submarine connector KONEKTA2
Key Environmental Issues
The environmental factors that the EIS developed by AZTI in 2008 considered key were hydrodynamics, landscape, benthic communities, ichthyofauna, marine mammals, fishing activity and archaeological and cultural resources.
The EIS developed by AZTI in 2018 for the use of BiMEP as a floating wind turbine testing facility considered that the main environmental factor that could be affected by the testing of offshore wind devices in BiMEP would be the marine birds communities protected under the ES0000490 Mundaka-Cabo de Ogoño Special Bird Protection Area. Consequently, an ambitious environmental monitoring plan over marine birds was suggested to be undertaken during the pre-operational, construction, operational and decommissioning phases.
Environmental reports and data resources:
Papers, Reports, Research Studies
Environmental Impact Studies and Monitoring Program reports (in Spanish) available through request to Basque Energy Agency (EVE, Ente Vasco de la Energía).
- A Bayesian Network model to identify suitable areas for offshore wave energy farms, in the framework of ecosystem approach to marine spatial planning
- SafeWAVE Deliverable 2.1 Development of environmental monitoring plans
- Acoustic characterization of submarine cable installation in the Biscay Marine Energy Platform (BiMEP)
- The Environmental Impact Study of the Biscay Marine Energy Platform (BiMEP) project
- Protocol to develop an environmental impact study of wave energy converters
- Environmental impacts over fish communities of submarine cable installation in the Biscay Marine Energy Platform (BiMEP)
- Underwater sound on wave & tidal test sites: improving knowledge of acoustic impact of Marine Energy Convertors
- Bald, J., A. Borja, J. Franco y C. Camba Rey, 2012. ESTUDIO DE INCIDENCIA AMBIENTAL y COMPATIBILIDAD CON LEY 41/2010, DE 29 DE DICIEMBRE, DE PROTECCIÓN DEL MEDIO MARINO DEL PROYECTO DE INSTALACIÓN DE UN AEROGENERADOR FLOTANTE EN LA INFRAESTRUCTURA bimep. 78 pp. (In Spanish)
- Informe de vigilancia ambiental de la fase de construcción del proyecto bimep. (In Spanish)
Baseline Assessment: Biscay Marine Energy Platform (BiMEP)
Receptor | Study Description | Design and Methods | Results | Status |
---|---|---|---|---|
Physical Environment, Sediment Transport | Sediment characterization. | Sediment sampling. | No significant contamination identified. Some sediment is expected to be suspended into the water column during construction, but localized and of short duration. This information involves a high resolution Digital Elevation Model (DEM) and topographic products derived, such as slopes’ map, shady digital elevation model, rugosity, topographic index, etc. | Completed |
Human Dimensions, Visual Impacts | Landscape characterization. | Characterization based on the catalog of Basque Landscapes. | Some significant landscape places near BiMEP. It is expected slight effects during installation and moderate effects during operation. | Completed |
Physical Environment, Water Quality | Hydrography characterization. | Water quality data analysis coming from the Littoral Water Quality Monitoring and Control Network of the Basque Country that AZTI-Tecnalia undertake since 1995 for the Department of Land Action and Environment of the Basque Government. | No significant contamination identified. It is not expected significant impact over water quality. | Completed |
Ecosystem Processes | Wave measurements and numerical modelling to predict the potential impacts of WEC devices on the wave regime. | Data generated from a measurement platform installed in BiMEP (Wavescan buoy of Fugro Oceanor) in March 2009, current meters and other buoys were employed. | Shoreline wave attenuations of 0-15% might be expected and limited local beach elevation changes were predicted to be limited to less than 0.2m. | Completed |
Human Dimensions, Fisheries | Fisheries characterization. | Commercial fisheries study (based on fish landing statistics, fisheries surveillance data, academic studies, previous fisheries reports) and consultation with local fishermen. | Short-term interference with fishing activity will be mitigated through navigation measures, Notices to Mariners, liaison with local fishermen and other measures. Potential interference of fishing gear (e.g. snagging) by the sub-sea cable. Exclusion of fishing activity from the deployment area and safety zones around the WECs, potentially displacing established fishing grounds and adding pressure to neighboring fishing areas. Prevention of fishing expected, however, to benefit fish resources within the area in which fishing is excluded and this has the potential to benefit fish resources outside the safety zones. | Completed |
Human Dimensions, Social & Economic Data | Archaeological resources characterization. | Consult on the Sub-aquatic Archaeological Catalog of the Basque Government. | A sunken vessel was identified near the BiMEP area. The shipwreck, identified as a German merchant sunk during WWII, is outside the finally licensed perimeter of the BiMEP area. | Completed |
Marine Mammals | Marine mammal survey. | Some data coming from sightings of AZTI-Tecnalia personnel in different sampling campaigns. | Not yet available. | Completed |
Fish | Literature review of impacts on fish. | Extensive bibliographic and web source information search was done. | No specific data available. Moorings, fixed prototypes to the bottom, dikes, docks and similar devices may cause noise and vibration, which generally scares away fish communities. During operation wave devices may cause noise and vibration, which generally scares away fish communities but generally speaking, any artifact located in the sea may cause an attraction effect on fish communities, especially if it is floating. | Completed |
Birds | Marine bird communities characterization. | No specific data available. Thus, an extensive bibliographic and web source information search was done. | BiMEP not sited in areas designated of international or national level of importance for seabirds. No significant impact on offshore birds is predicted during brief construction activities. Similarly, no significant impact was predicted during operation because of the relatively small-scale of the development in the context of the surrounding open sea area. | Completed |
Birds | Marine bird monitoring. | Biweekly monitoring of seabirds in BiMEP during one year (2016-2017). | Not publicly available. | Completed |
Invertebrates | Benthic communities characterization (soft and hard bottom). | Benthic communities sampling with grab in soft sediments and analysis with AZTI Marine Biotic Index. For hard bottom communities, sampling was done in several intertidal sampling stations. | Benthic community in slight disequilibrium due to the high hydrodynamics of the area. Alteration to benthic communities are expected due to: (i) direct destruction; (ii) alteration in the proportion of hard-soft substratum, (iii) dragging action of anchors and ends; etc | Completed |
Post-Installation Monitoring: Biscay Marine Energy Platform (BiMEP)
Stressor | Receptor | Study Description | Design and Methods | Results | Status |
---|---|---|---|---|---|
Noise | Marine Mammals | Marine mammal monitoring by observers during installation works | Marine mammal monitoring is carried out fortnightly in BiMEP. This was reinforced during the installation works of the Penguin device, with particular focus on potentially noisy operations. | No marine mammals were detected by the observers during installation works | Completed |
Collision | Birds, Marine Mammals | Fortnightly monitoring of marine bird communities and marine mammals. | Monitoring of key marine bird communities is carried out in BiMEP on a regular basis, approximately every 2 weeks. | Ongoing since September 2016 | |
EMF | Physical Environment | Electromagnetic Fields (EMF) detection from MARMOK-A device within the WESE project. | The EMF monitoring was done with the collaboration of MAPPEM Geophysics (www.mappem-geophysics.com) using a towed ‘fish’, including 4 channels for very high sensitivity electric field dipoles and a 3-axes fluxgate magnetometer. Data were recorded at 2 kHz. The system is also equipped with attitude and navigation sensors to recalculate its position underwater (2-axes tilt meters, pressure depth sensor and altimeter). Different transects over the cables providing service to the MARMOK-A-5 of IDOM-Oceantec were followed for EMF data acquisition. | Report available on http://wese-project.eu/ Data available on marendata.eu | Completed |
Changes in Flow | Physical Environment, Sediment Transport | Seafloor integrity assessment from MARMOK-A device within the WESE project. | To evaluate possible alterations of the seabed integrity by the moorings and mooring lines of the MARMOK-A-5 device in BiMEP, a side scan sonar survey and a visual inspection with a ROV were undertaken with the collaboration of Ekocean Servicios Marinos (www.ekocean.es) providing the boat needed for the campaign (12 m length vessel) and ESGEMAR S.A. Estudios Geológicos Marinos (www.esgemar.com), in charge of the Side Scan sonar monitoring, and Instalsub (www.instalsub.com/), in charge of the ROV inspection. | Report available on http://wese-project.eu/ Data available on marendata.eu | Completed |
Changes in Flow | Physical Environment, Sediment Transport | Seafloor integrity assessment from Penguin device within the SAFEWAVE project. | To evaluate possible alterations of the seabed integrity by the moorings and mooring lines of the Penguin device in BiMEP, a side scan sonar survey (SSS) and a visual inspection with a ROV were undertaken. The SSS campaign was carried out by RTSys, with a SSS instrument mounted on their AUV Comet and the ROV campaign was completed by Azti with their ROV. | Data analysis ongoing, report underway. Preliminary results available at marendata.eu | Completed |
Habitat Change | Fish | Impact on fish communities due to potential reef effect of floating devices. | The potential aggregation effects of floating structures on fish was studied with different techniques. First, in August 2022, the ITSASDRONE, purpose-built autonomous catamaran with a WBAT sound was deployed in BiMEP. It completed several transects arounf the Harshlab floating laboratory and in a control area within BiMEP. Later, in summer 2023 WBAT sound was mounted on the Harshlab device. | Preliminary results available at https://www.safewave-project.eu/project-outputs/ | Ongoing |
EMF, Noise | Fish | Active acoustics studies on fish and impacts of submarine cable installation in BiMEP. | Active acoustic methods: five M3i buoys, developed by Marine Instruments (www.marineinstruments.es), were installed from June 2012 to December 2013 in the area, one in each of the four mooring areas and one far enough from BiMEP area to act as control site. The M3i buoys are equipped with a GPS and echo-sounder (50 kHz and 500 W) and solar panels as their energy source. While the GPS of the buoy allows tracking the position of the buoy itself, the echo-sounder allows measuring the relative biomass below the buoy. | Fish shoals more abundant during summer months, up to 30 m depth and in the proximity of Buoy 1, which is the nearest buoy to the submarine mountain named “Seabass Island”. It is known for concentrating great fish biomass. No differences were observed in the number of fish shoal detected before, during and after the cable installation works. | Completed |
Noise | Physical Environment | Underwater noise assessment during the installation of DEMOSATH. | A hydrophone was moored in BiMEP to capture the underwater noise during the device installation works, from September to October 2022. | Not yet published. | Completed |
EMF, Habitat Change, Noise | Invertebrates | Impact of benthic communities and seabed characteristics from submarine cable installation in BiMEP. | The characterization of benthic communities was done in May 2014 by means of: (i) in situ sampling with a Shipeck grab sampler soft bottom sediments in five locations (4 samples inside the BiMEP area and one outside, in order to act as control area) and by divers in five locations near the landing point of the submarine cable (Figure 2) and (ii) visual inspection with a submarine camera in 36 points distributed along the submarine cable route and the mooring areas. | No significant alterations were observed in most part of the cable route over the seafloor and benthic communities. The cable remained on the seafloor or was buried by sediment dynamics. In some parts the cable was laid over rocky substratum but no impacts on the benthic communities were observed. | Completed |
Collision | Birds | DTBird device installed on the DemoSATH. | Since the commissioning of the DemoSATH device in BiMEP in September 2023, the DTBird device has been in operation. The device detects fligths of birds and emits deterring sounds for the birds to change their route and avoid collision. The accuracy of the detections and the ratio of false positives is being analysed. | Not yet available. | Ongoing since 2023. |
Noise | Marine Mammals, Physical Environment | Acoustic characterization of submarine cable installation in BiMEP. | Two sampling campaigns were completed: (i) a baseline acoustic campaign prior to cable installation; (ii) a second campaign during the installation of one of the submarine cables. The sampling campaign was carried out with an icListen HF 200 kHz hydrophone of Ocean Sonics (http://oceansonics.com/). In each campaign 5 minutes measurements at 10 m depth were taken in 15 sampling points along the cable route. | Sound background levels between 70-80 dB; During cable installation an increase of the average sound can be observed in low frequencies: 140 dB in 11 kHz, about 30 dB above the background level in this frequency. | Completed |
Collision | Birds | European storm petrel tagging campaign. | In the summer of 2023 20 individuals of European storm petrel were captured and tagged with nanoGPS devices in order to study their feeding habits and assess the potential impact of the presence of floating wind turbines on their feeding routes. 5 of these nanoGPS devices were retrieved in subsequent campaigns and data from 9 feeding trips were analysed. | Not yet published. | Completed |
Noise | Physical Environment | Underwater noise assessment from the MARMOK-A device within the WESE project | Underwater sound emissions were monitored by means of a combination of static, mobile and airborne measurements. Static measurements consist in the deployment of a passive acoustic sensor moored in a specific location and for a long period of time. A SoundTrap ST300 HF of Ocean Instruments was moored on the 7th May 2019 for a period of 41 days. The hydrophone recorded for 10 minutes every hour at a sample rate of 288 kHz. Mobile surveys consist on passive acoustic measurements in different locations (17 sampling stations) during a short period of time (5 minutes in each sampling station). The same equipment was used (SoundTrap ST300 HF). This campaign was completed on the 7th May 2019. Airborne measurements were made in the same locations and time period of that of the mobile surveys with a specific equipment developed by CTN of Cartagena (Spain). CTD profiles were obtained to calculate density and sound speed profiles to support underwater sound propagation analysis. | Report available on http://wese-project.eu/ Data available on marendata.eu | Completed |
Noise | Physical Environment | Underwater noise assessment from the Penguin device within the SAFEWAVE project. | A hydrophone was moored in BiMEP to capture the underwater noise during the device installation works, from June to August 2021, within the SAFEWAVE Project. Later, 3 hydrophones were installed to capture noise during the operation of the device, between November 2021 and January 2022. | Data analysis ongoing, report underway. Sample recordings available at marendata.eu | Completed |