Abstract
Article 401 of the Pilot Project License for the Roosevelt Island Tidal Energy (RITE) Project
(FERC No. P-12611) specifically approved the six RITE Monitoring of Environmental Effects
(RMEE) plans as shown on Table 1, and notes that they cannot be amended without Commission
approval.
Following review and adaptive management consultation (see Appendix A), and agency
concurrence (see Appendix B), Verdant requests Commission approval of the proposed
modifications to the RMEE plans described in this document for implementation during the
RITE Install B-1 Pilot Project in 2020.