The Project One Companies require an amendment to the Hornsea Project One name plate capacity by 1.5% from 1,200MW to 1,218MW and an amendment to the limits of deviation of the wind farm areas within the overall consented Order Limits in order to amend the internal boundaries of Wind Farm Areas 1, 2 and 3. This document outlines the reasons for the changes sought and the implications of the proposed changes and the case for these changes constituting a non-material amendment to the Hornsea Project One DCO and Deemed Marine Licences (DML) 1, 2 and 3, though the DMLs will be dealt with through a separate process.
This document is related to the Hornsea 1 Wind Farm Project Site.